DPM Metals Announces Robust Feasibility Study Results for the Čoka Rakita Project with $782M of NPV5% and 36% IRR
View original at globenewswire.comDPM Metals Announces Robust Feasibility Study Results for the Čoka Rakita Project with $782M of NPV5% and 36% IRR TORONTO, Nov. 26, 2025 (GLOBE NEWSWIRE) -- DPM Metals Inc…
What we drew from this source
The claims Via News extracted from this document. We point to the source; we don't replace it.
Average annual gold production of 148K oz over life of mine with first 5 years averaging 189K oz
80% confidenceProject economics show NPV of $2,207M at $3,500/oz gold with 67.8% IRR
80% confidenceAll-in sustaining cost is $644/oz placing project in first quartile
80% confidenceProject will create 500+ jobs with focus on local hiring and training
80% confidenceMineral reserves increased 10% in tonnage and 11% in contained ounces compared to PFS
80% confidenceFeasibility study assumes 0% corporate tax for 10-year mine life under Serbia large investment relief
80% confidenceFeasibility study completed in less than 36 months from discovery announcement
80% confidenceČoka Rakita project has after-tax NPV of $782M at $1,900/oz gold with 36% IRR and 1.8 year payback